(ii) group b: tenders offered by other tenderers.
(b) for the purpose of further evaluation and comparison of tendersonly, an amount equal to _________ percent of the tender price (asadjusted pursuant to paragraphs (a), (b) and (c) of sub-clause 28.2) willbe added tothe evaluated tender price of tenders classified in group b.
award of contract30. award criteria
subject to clause 31, the employer and ________ company may award thecontract to the tenderer whose tender has been determined to besubstantially responsive to the tendering documents and who has offeredthe lowest evaluated tender price pursuant to clause 28 and paragraph (b)of sub-clause 29.3 (if applicable), provided further that the tenderer hasthe capability and resources to carry out the contract effectively (referto sub-clause 3.5), butthe employer and _________ company gives noguarantee that the lowest orany tender will be accepted.31. employer's rights
notwithstanding clause 30, the employer reserves the right to acceptor reject any tender, and to annul the tendering process and reject alltenders, at any time prior to award of contract, without thereby incurringany liability to the affected tenderer or tenderers or any obligation toinform the affected tenderer or tenderers of the grounds for theemployer's action.32. notification of award
32.1 prior to the expiration of the period of tender validityprescribed by the employer, the employer will notify the successfultenderer by telex or telegram confirmed in writing by registered letterthat his tender has been accepted. this letter (hereinafter and in theconditions of contract called the "letter of acceptance") shall name thesum which the employer will pay to the contractor in consideration of theexecution, completion and maintenance of the works by the contractor asprescribed by the contract (hereinafter and in the conditions of contractcalled the "tender sum").
32.2 the notification of award will constitute the formation of thecontract.
32.3 upon the furnishing by the successful tenderer of a performancesecurity in accordance with the provisions of clause 34 hereof, theemployer will promptly notify the other tenderers that their tenders havebeen unsuccessful.33. signing of agreement
33.1 within ________ days of notifying the successful tenderer thathistender has been accepted, the employer will send to the tenderer twocopies of the form of agreement provided in the tender documents,incorporating all agreements between the parties.
33.2 within__________ days of receipt of the form of agreement, thesuccessful tenderer shall execute the agreement by signing or sealing, asappropriate, and return both copies to the employer. the employer willthen execute the agreement and return one copy to the contractor.34. performance security
34.1 within _________ days of receipt of the letter of acceptance, thesuccessful tenderer shall furnish to the employer a security for the dueperformance of the contract, in accordance with the conditions ofcontract. the form of performance security provided in the tenderdocuments may be used, or some other form acceptable to the employer.
上一页 [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] 下一页
Tag:招标合同,招标合同范本,工程招标合同,合同范本 - 招标合同
- 国际工程招标说明书格式(英文)